LOCATION: South side of Arapahoe Road approximately one-quarter mile west of Highway 287.
SIZE: 80 acres
PLANNED USE: 453 single-family and multi-family homes and less than 10,000 square feet of neighborhood commercial primarily associated with the proposed CSA farm.
PHASING: Home will be built in several phases.
DEVELOPMENT PROCESS:
- Project Sketch Plan and Rezoning were approved in December 2015
- Annexation application was approved in May 2016
- Preliminary Plan was approved by the Planning Commission in November 2016
- Final Plan was approved by City Council on Oct. 17, 2017
- City Council granted a recording extension for the Silo Subdivision Final Plan because of delays involving the ditch-related agreements and engineering for the project. The final plan was recorded in April 2020.
CURRENTLY UNDER REVIEW: A change to a portion of the site plan and plat is currently under review. This will also affect the PUD site plan.
PROJECT REVIEW
Planning Commission recommended approval of the Vacation of Rights-of-Way and Easements for Silo Subdivision Filing No. 1 at their August 25, 2021 meeting.
City Council approved Silo Subdivision Filing No. 1 Replat A and the Vacation of Rights-of-Way and Easements at their November 16, 2021 meeting.